What is modular construction, and why has Chapman Taylor embraced it?

Drawing on his experience working on Chapman Taylor’s first off-site volumetric construction project, as well as his role in developing the company’s trademarked Umbrellahaus® prototype, Associate Director Michael Swiszczowski talks about modular construction, particularly the role it has to play in addressing the UK’s building capacity problem.

What is modular construction?

Modular construction is a form of off-site construction in which a building’s components, or modules, are constructed in a factory setting before being transported to site for assembly. People are most familiar with this type of construction in the use of bathroom pods, which is a common method of construction in many residential and hospitality projects.

In recent years, we have seen a rise in the use of volumetric construction, which involves the off-site construction of as much of a building as possible before being brought to site. Typically, a volumetric project would construct a complete room, with a bathroom inside that room, as well as part of the corridor and, perhaps, some external finishes.

What are the types of modular construction?

If you imagine a scale from traditional on-site construction to full-scale off-site construction, bathroom pod construction is much nearer the former, with most of the building still constructed on site in a traditional manner. Unitised façade systems and external envelopes are further towards the middle of the scale, and these have been produced partly off-site for decades. Further along are “flat-pack” solutions, involving the use of cross-laminated timber or concrete cross-wall construction. Typically, these structures would be constructed in panelised pieces off-site, then delivered flat on a vehicle to be assembled on site.

In terms of the housing shortage, volumetric modular construction has a key role to play in pushing the industry forward.

Modular construction involves the delivery of factory-finished container sections to site for assembly

Finally, there is volumetric construction, where the majority of the building components are fabricated off-site in factory-controlled conditions before delivery to site. With volumetric, all the internal finishes arrive completed, which is very useful for developments in areas such as student housing or hospitality because there are no ‘wet trades’ coming onto site after delivery. This greatly reduces the number of people on site and the length of the programme, as well as providing programme certainty.

Chapman Taylor is confident working with any of these methods, noting that modular solutions may not be appropriate in all instances. We don’t tie ourselves in with any particular provider, and we will advise clients and others in a way which best suits the requirements of the particular site logistics and project brief. However, we do think that, in order to address the UK’s capacity issue, particularly in terms of the housing shortage, volumetric modular construction has a key role to play in pushing the industry forward.

 What are the benefits of off-site construction in general, and volumetric in particular?

Off-site construction has a number of benefits in terms of programme, waste, cost and, of particular interest to us, quality. The building’s elements can be constructed a lot more quickly in controlled conditions – if necessary, the process can continue 24/7 and involve finished products continuously rolling off the factory floor. The process is not governed by some factors present in traditional builds, such as adverse weather, challenging site logistics, the industry’s skills shortage, etc. The factory process will often involve people specialising in one specific area to a very high standard, leading to a better quality of product. The speed of the programme leads to earlier project completion.

Waste can be significantly reduced with an off-site process – as much as 50% of waste on traditional building sites could be prevented by a switch to off-site construction, with all the attendant financial and environmental benefits. Meanwhile, there are attractive economic advantages for the developer– in today’s market, it isn’t necessarily always cheaper to build off-site in the first instance, but the benefits to the client then accrue in a number of ways.

With our Holiday Inn Express modular hotel project in Trafford City, Manchester, it was just nine months from the start of the construction process on site to completion, saving six months of construction time compared to the traditional build programme. This resulted in the client avoiding six months’ worth of interest payments on loans and only paying the contractors for a relatively short amount of time on site. It also meant that they were able to start trading six months earlier, with all the associated revenue generation that brought about.

With a hotel, a Build-to-Rent scheme or student accommodation, where space is rented, a substantial income will be generated a lot earlier because of the use of off-site methods.

The factory-finished modules are lifted into place in line with a precise programme schedule.

What are the benefits of off-site construction in general, and volumetric in particular?

Off-site construction has a number of benefits in terms of programme, waste, cost and, of particular interest to us, quality. The building’s elements can be constructed a lot more quickly in controlled conditions – if necessary, the process can continue 24/7 and involve finished products continuously rolling off the factory floor. The process is not governed by some external factors present in traditional builds, such as adverse weather, challenging site logistics, the industry’s skills shortage, etc. The factory process will often involve people specialising in one specific area to a very high standard, leading to a better quality of product. The speed of the programme leads to earlier project completion.

Waste can be significantly reduced with an off-site process – as much as 50% of waste on traditional building sites could be prevented by a switch to off-site construction, with all the attendant financial and environmental benefits. Meanwhile, there are attractive economic advantages for the developer– in today’s market, it isn’t necessarily always cheaper to build off-site in the first instance, but the benefits to the client then accrue in a number of ways.

With our Holiday Inn Express modular hotel project in Trafford City, Manchester, it took just nine months from the start of the construction process on site to completion, saving six months of construction time compared to the traditional build programme. This resulted in the client avoiding six months’ worth of interest payments on loans and only paying the contractors for a relatively short amount of time on site. It also meant that they were able to start trading six months earlier, with all the associated revenue generation that brought about.

​The client estimates that they saved approximately £1 million in costs when compared to a traditional form of construction, and told us that they had never been involved in a project which was so stress-free.

Holiday Inn Express in Trafford City

The client estimates that, taking all of these financial aspects into account, they saved approximately £1 million in costs when compared to a traditional form of construction, which is particularly impressive in the context of the overall project cost of £16.2 million. The original development team, which was a joint venture between Mill Lane Estates, Marick and Topland, was able to sell the  hotel before practical completion because the fully finished bedroom pods were installed early on during the build programme.

With a hotel, a Build-to-Rent scheme or student accommodation, where space is rented, a substantial income will be generated a lot earlier because of the use of off-site methods. In addition, on the building contract side, the shorter building schedule means lower labour costs and reduced overheads. Investors get a return on their investment much more quickly, paying less in interest on loans.

Tell us some more about how the Holiday Inn Express project came about?

The Holiday Inn Express project came to us through the principal contractor, Bowmer & Kirkland. Planning had been achieved for a hotel at the Holiday Inn Express site, but the client wanted to change to a volumetric modular approach, and Bowmer & Kirkland were eager for us to come on board because they needed a firm of architects with which they were comfortable working and which had the skills to work on a project of this type.

InterContinental Hotels Group’s Holiday Inn Express brand was in the process of launching its new generation of hotel design – a modern, clean and simple approach tailored for today’s ‘smart traveller’. Ours was to be the first, new-build, ‘Generation IV’ design in the UK.

Modular bedroom unit at Holiday Inn Express, Trafford City

We started on a steep learning curve to understand the original design intent and the implications of adopting a volumetric modular approach, which would use a purpose-built container system by CIMC Modular Building Systems. We built a new BIM model in Revit, incorporating the container elements, and had to answer some key requests for information to allow the factory to start procuring the material for a prototype – all in the first three weeks. It was an ambitious beginning to the project, but we delivered all the information on time.

We took meticulous care with our advice to CIMC, the Chinese modular container provider, ensuring that the pods were up to British building regulation standards. As a result, we formed a very strong working relationship with CIMC and are now working with them as a consultant on other projects around the world.

It was a fabulous project to be involved in, and it progressed at pace, but in a smooth and controlled manner. The client told us that they had never been involved in a project which was so stress-free. It was a great testament to what modular construction can achieve. Happily, the project won a major off-site industry award recently – “Retail/Leisure Project of the Year” at the 2018 Offsite Construction Awards – as well as being highly commended in another category.

Delivery of steel containers to Trafford City site

What happened after the project?

Everyone who worked on the project got together afterwards to take part in a ‘lessons learned’ meeting. It was a very useful debriefing session, and helped us all to hone our approach to future projects. Chapman Taylor has a research and development model for modular construction, called Umbrellahaus®, and the lessons learned on the Holiday Inn Express development has helped advance that.

The project acted as a gateway to the world of modular construction, and we decided that we should talk to several modular providers about the many different possible methods to learn as widely as we could. We learned about some of the nuances which arise when using a modular approach to construction – there are situations which arise with modular construction that you don’t usually come across with traditional projects, which typically follow a very linear RIBA plan of work format, and it is these challenging situations which require subtle and imaginative solutions as well as a flexible attitude to approaching design and construction in new ways.

People are now paying much more attention to quality than ever before, and modular construction fits naturally into the picture.

Assembly of purpose-built modular containers on site at Trafford City

Is the finished product as good as with traditional construction?

Better. In terms of the materials and the quality of finishing, everyone was delighted by the end result at the Holiday Inn Express building. There were some minor snagging issues, but a fraction of the number that would normally arise, all of which were resolved very quickly. The process was incredibly efficient and the whole team was very relaxed in the run-up to the final handover, which is unusual on a project of that size. The hotel, operated by Tower Hotel Management, achieved Practical Completion on time, and was fully booked for its opening weekend. It has been trading successfully ever since.

We are working with many leading developers and modular manufacturers on projects across the residential, student accommodation and hospitality sectors​.

Holiday Inn Express lobby seating area

It can also lead to better environmental credentials – you are more likely to get a well-sealed and airtight system, allowing for a much lower energy requirement.

Following the opening, we have shown several developers, contractors and facility managers around the finished building, and they have always been impressed by its quality.

Many people have a negative association with the term ‘prefab’, which they associate with substandard post-war buildings. How is modular different?

It is certainly the case that there is a perception out there which needs to be shifted, one which associates off-site construction with the prefab of old. Modular is not prefab. Of course, pre-fabrication was a form of modular process – it involved construction off-site – but the design and construction process involved with modular construction is vastly superior, and there is a very different business case for it.

We have a crisis in the UK with housing capacity – there is a severe housing and skills shortage. Modular construction is one means of addressing that, capable of increasing the number of homes which can be delivered each year. Modular is also becoming much more relevant because of the increase in Build-to-Rent schemes, which are residential developments where the investors and developers retain and operate the building for its lifetime, rather than just flipping it for a sale when built.

There is much more focus on quality and on maintenance of the product for the lifecycle of the building. For example, pets are a major consideration in the Build-to-Rent sector – requiring the finishes to be approached differently. People are now paying much more attention to quality than ever before, and modular construction fits naturally into the picture. So it bears little relation to the lower-quality prefab buildings we saw in the decades after the Second World War.

Off-site may have been around for decades, but the reasons why people are interested in it are very different now, and the people involved are different – not just manufacturers, but also large institutional investors. Legal and General, for example, have announced their own modular factory, and Berkeley Group are also getting involved in the sector. The Farmer Review has helped by stressing the need for the construction industry to ‘modernise or die’, as has the mention of off-site construction in the UK government white paper aimed at ‘fixing our broken housing market’.

We have had very positive discussions with, for example, the Mayor of London’s office and various local authorities, which are keen to promote modern methods of construction as one means of dealing with the housing crisis. The former Director of Housing in Manchester City Council is also an advocate of the benefits of modular construction, and wants to see residential developers adopting this approach.

How well-placed is Chapman Taylor in the modular sector

We have been investing in R&D initiatives relating to the modular sector for some time, and we are now able to complement that knowledge with practical experience of modular design and construction processes. By working collaboratively with other stakeholders, local authorities, consultants, contractors and modular suppliers, we are able to offer comprehensive advice to our clients for each individual project, across our core sectors. We have published several insight papers on the subject, which have proved to be very popular.

We are increasingly viewed as experts in the modular sector, and we are working with many leading developers and modular manufacturers on projects across the residential, student accommodation and hospitality sectors. The key to our continued success will be to collaborate with our peers and strive for constant improvement in everything we do. Ultimately, it’s all about engaging with like-minded people in order to implement the step-change our industry so desperately requires.

How have Chapman Taylor’s clients responded?

Clients are keen to understand more about modular solutions and about how their project could benefit from these. Chapman Taylor is able to offer an impartial view and advice based on experience, which is very valuable in such a new market.

Technology is permeating our culture at a rapid rate, creating an impact upon many aspects of our lives. The modular approach to construction could be the next big disruption to our industry. We should embrace this and learn how to make best use of this technology to create well-designed buildings that meet the needs of our clients for both the immediate and long-term.

What next for Chapman Taylor and modular?

We are working on several modular projects for the Build-to-Rent, student accommodation and hotel sectors. Some are in the early concept stages, and others are existing schemes for which we are looking to develop modular solutions – we are advising clients on the technical design options while respecting the original designs, which have planning approval.

Ultimately, it’s all about engaging with like-minded people in order to implement the step-change our industry so desperately requires.

Concept sketch for a modular housing project

Our expertise in the use of 3D BIM technology is proving invaluable for our modular work; we can quickly generate design studies and present them in a 3D format to allow our clients to visualise the proposals early on in the design process. This then seamlessly follows into the more technical aspects, where we can generate models and components which are used by the fabrication team in the factory for construction.

Chapman Taylor is convinced of the potential benefits of this exciting sector for designers, clients and end-users alike, and we look forward to being part of the next phases in the evolution of modular construction, in collaboration with our clients and other stakeholders.

About the Author

Michael Swiszczowski (BA(Hons), MArch, ADPPA, ARB, RIBA)

Director, 曼彻斯特

Michael joined Chapman Taylor in 2016 to strengthen the practice’s residential expertise. A key member of the Manchester studio’s management team, Michael has a business development remit for the residential sector across the UK business.

He has experience working on award-winning residential projects with a particular focus on build-to-rent, student accommodation and modular construction.

He is a RIBA-elected member of the Regional Council for RIBA North West.

Areas of expertise:

Residential / Build-to-Rent / Student Accommodation / Hotels

Related Projects

All Projects
caret-down-skewed caret-down-thin caret-down caret-left-thick caret-left-white caret-left caret-right-thick caret-right-white caret-right caret-up chinese cross download english facebook grid instagram linked-in list mail map pinterest play-button reset search-nobg search-square share twitter views wechat youtube